They have been focusing on four areas of the project, including the surface water drainage with the installation of the second water tank. The foundation of the first building is nearly completed, with attention now being drawn to the ground-floor concrete slabs.
The slab works on the ground floor of the second building however are well underway. Regarding the infrastructure site as a whole, the excavating of trenches and ducting have begun.
The contractor posted: “Since our last update in April, the site has made significant progress over the past four months."
...huge credit to the whole team for their continued hard work, commitment, and focus.
“The site team continue to consistently meet key milestone dates, enabling follow-on trades to progress their works in line with the construction programme. A huge credit to the whole team for their continued hard work, commitment and focus.”
The redevelopment of Castle Leazes is a joint venture between Newcastle University and Unite Students, the largest provider of purpose-built student accommodation in the UK.
In June this year, the Freemen of Newcastle were shown the construction site where they signed a steel beam that will be incorporated into the two buildings’ structure – both of which will be completed for the 2028/2029 academic year.
The guardians of the city have overseen Newcastle’s moors and open spaces for more than 800 years, and are represented by David Wilson who is chair.
Nick Collins, Chief Financial Officer at Newcastle University, said: “The project has been made possible through a strong collaborative effort with a number of key stakeholders in the city, including the Freemen of Newcastle, Newcastle City Council, our local councillors, and many others like our funders Rothesay.
“So we were delighted to show them the progress we’re making on construction and to explain how the project will contribute to preserving the Castle Leazes site for the future as well as provide significant benefits to the city’s economy.”